Schedule Delay!

Monday, February 4th, 2008

We knew it was coming, and our first delay has occurred. We had to email the sales rep to get the info, as the website just showed a one week delay starting next week for all items after the 1st floor framing. (I will update our calendar within the next week or so) Here’s the update:

Weekly Update

There was slight delay in schedule due to waiting for the inspection required from the township. Received OK from inspector to proceed with construction and framing is scheduled to begin on Monday.

Apparently, the schedule is just bufferred by the week. The actual time delay isn’t really known yet!

- James

Permit Application

Friday, December 14th, 2007

3 days ago (12/10), our permit was applied for…. we should expect it back in approx. 3 weeks.

Yes, this is painful!!!!! lol. With that in mind, on a normal calendar, we should get it on New Years Eve 12/31/07. However… I wouldn’t be surprised if a few days got bumped due to the holiday.

They were though, early, in providing our drafts, so fingers are crossed!

With that in mind, we should expect to break ground about the 2nd week of January.. hopefully by Monday 1/14/08! Fingers crossed for a good REST of the winter! (What we’ve had so far does NOT COUNT!)

~ Marissa ~